Goals
Mechanical Goals
- Produce 7 more axles
- Finish production of jellyfish
- full scale assembly
Software Goals
- Polish control code
- Finish website
- Solder and mount electronics
Deliverable
Leading up to Demo Day we leaned hard into manufacturing and assembling the final piece - the goal was to get from our single Sprint 3 shaft, to a full 8 shafts. To accomplish this, we:
- Got every shaft welded
- Attached all pulleys to shafts
- Tied all jellyfish to pulleys
- Attached all shafts to the frame.
On the morning of Demo Day, we had all 8 shafts mounted, and were ready to go. Then, disaster struck. Our shafts weren't fully secured to the motor / shaft interfaces and several fell off, damaging components in the process. We scrambled to replace the broken pieces. And, by the end of our demo period we had 6 shafts back up, running and reacting!